A vendor data requirement schedule is an itemized list of vendor
data requirements for a package or requisition. Generally the
vendor data requirements are selected from the standard library
for both speed and accuracy purposes. Initially the VDR schedule
is defined as Pre-award so it can be included as part
of a bid package document. Once a contract is awarded, the status
changes to Post-award for ongoing control.
Against it each vendor data requirement (VDR) it is possible
to define:
Purpose: This is typically used to distinguish between issues
of vendor data as preliminary and certified.
Format: Used to specify the format in which the vendor data is
to be supplied.
Copies: Used to specify the number of copies to be submitted.
Weeks After: Used to specify when the vendor data is required
in relation to defined Milestones. 4A for example indicates that
this item is required 4 weeks after award milestone. 2D
would mean two weeks before delivery.
With Bid: Preliminary data to be submitted together with the
bid.
With MDR: To be submitted together with the Manufacturing Data
Record.
With IOM: To be submitted together with the Installation and
operating manuals.
Details: Details associated with this VDR Code.
Response Period: Days required for a response.
|